Round Bald Relocation / Stairway to Heaven (2000-2001)

During 2000-2001, the A.T. on Round Bald was relocated and rehabilitated, to eliminate significant erosion problems and replace the former steep route with a more gradual sidehill trail. The project has three distinct phases:

  • Phase 1 – Gravel delivery and trail construction from Carvers Gap to a large rock about two-thirds of the way up to the summit of Round Bald – summer of 2000.
  • Phase 2 – Gravel delivery between the large rock and Engine Gap – February-March 2001.
  • Phase 3 – Spreading the gravel on the existing Trail route between the large rock and Engine Gap – summer of 2001.

Continue reading “Round Bald Relocation / Stairway to Heaven (2000-2001)”

Laurel Fork Gorge Bridge Replacement (1999)

On January 7-8, 1998, torrential rains struck northeast Tennessee and western North Carolina. Carter County, Tennessee was hit especially hard, with widespread flooding and seven deaths caused by ten inches of rain during a 24 hour period. The lower two bridges on the A.T. in Laurel Fork Gorge were completely destroyed. The center span of the upper bridge (the Koonford Bridge) was also destroyed, but temporary repairs were quickly made by TEHCC on January 17, 1998. A temporary blue-blazed route for the A.T. to bypass the two destroyed bridges was completed in May 1998. Continue reading “Laurel Fork Gorge Bridge Replacement (1999)”